Which is an appropriate fix when static timing analysis finds a setup violation?

  1. AReduce delay by simplifying the logic on the path or switching to cells with higher drive strength
  2. BIncrease delay by adding delay buffers to the path
  3. CRaise the clock frequency
Show answer and explanation

Answer: A. Reduce delay by simplifying the logic on the path or switching to cells with higher drive strength

A setup violation occurs when the data path is long and data does not arrive before the next clock. Delay is reduced by cutting logic levels, switching to stronger cells, or placing cells closer to shorten wires. Lowering the clock frequency also resolves it. Increasing delay is the fix for hold violations.

Practice this topic Back to topic

More LSI design flow and EDA questions

  1. Why is static timing analysis performed under multiple conditions combining process variation, supply voltage and temperature?
  2. What is the step called that extracts wire resistance and capacitance from the layout after place and route?
  3. In verifying large SoCs, which technique runs the designed circuit on dedicated hardware or FPGAs and verifies it quickly together with software?
  4. What is it called to hand over the data for mask making to manufacturing after design and verification are complete?
  5. In the final check before tape-out (sign-off), which power-network analysis is performed alongside timing verification?