Which of the following is an appropriate way to carry out change management?
- AChanges to the production environment may be made at any time without keeping records, whenever the person in charge judges them necessary
- BChange requests are recorded, assessed for impact, risk and cost, and approved before being carried out according to plan
- CChanges are approved together after they have been carried out
Show answer and explanation
Answer: B. Change requests are recorded, assessed for impact, risk and cost, and approved before being carried out according to plan
Change management is the process for preventing failures caused by changes, in which changes to IT services and their components are recorded, assessed for impact, risk and cost, and approved before being carried out. Change requests are recorded when received and, depending on their content, reviewed at a meeting of the people concerned. After implementation, the result is checked, the change is recorded and the configuration management information is updated.
- A. Changes with no record or assessment cause failures and make it impossible to trace later what was changed.
- B. Correct. Changes are carried out according to plan after being recorded, assessed and approved.
- C. Approval comes before implementation. Approving afterward does not prevent failures caused by the change.