Software Development and Project Management

The SLA for a service specifies a monthly availability of at least 99.95%. A month is taken as 30 days, and planned downtime is included in the calculation. This month the service has already been down for a total of 15 minutes due to failures. How much more downtime is allowed for the rest of this month while still meeting the SLA?

  1. A6.6 minutes
  2. B21.6 minutes
  3. C36.6 minutes
Show answer and explanation

Answer: A. 6.6 minutes

A month is 30 × 24 × 60 = 43,200 minutes, and at 99.95% availability the allowed downtime is 43,200 × 0.0005 = 21.6 minutes. Since 15 minutes have already been used, 21.6 − 15 = 6.6 minutes remain. 21.6 minutes forgets to subtract the downtime that has already occurred, and 36.6 minutes adds it instead of subtracting it. An SLA should specify, as agreed between the service provider and the user, matters such as whether planned downtime counts toward availability and the measurement period.

  • A. Correct. Up to 21.6 minutes of downtime is allowed per month, and 15 have been used, leaving 6.6 minutes.
  • B. This is the downtime allowed for the whole month, without subtracting the 15 minutes already used.
  • C. This adds the 15 minutes already used instead of subtracting them.
Practice this topic Back to topic

Related calculators

Books on Software Development and Project Management Ad

As an Amazon Associate I earn from qualifying purchases.

More Software Development and Project Management questions

  1. In IT service management, which process mainly aims to investigate the root cause of recurring failures and prevent them from happening again through permanent fixes?
  2. Which is a characteristic of the waterfall model of software development?
  3. In the V-model of software development, which test corresponds to the requirements definition phase and checks that what was decided in that phase is satisfied?
  4. In Scrum, which role is accountable for the content and ordering (priority) of the Product Backlog items and for maximizing the value of the product?
  5. In Scrum, which event takes place at the end of a Sprint to show the completed Increment (the working product) to stakeholders, gather feedback and adjust future direction and the Product Backlog?