Software Development and Project Management

In a project with a budget at completion (BAC) of ¥20 million, at a certain point the planned value (PV) was ¥8 million, the earned value (EV) ¥6 million and the actual cost (AC) ¥7.5 million. Which correctly describes the project's status at that point?

  1. AIt is behind schedule (SPI = 0.75) and over budget (CPI = 0.8)
  2. BIt is behind schedule (SPI = 0.75) but within budget (CPI = 1.25)
  3. CIt is ahead of schedule (SPI = 1.33) but over budget (CPI = 0.8)
Show answer and explanation

Answer: A. It is behind schedule (SPI = 0.75) and over budget (CPI = 0.8)

The schedule performance index is SPI = EV ÷ PV = 6 ÷ 8 = 0.75, which is less than 1, so the project is behind schedule (schedule variance SV = EV − PV = −¥2 million). The cost performance index is CPI = EV ÷ AC = 6 ÷ 7.5 = 0.8, which is less than 1, so more has been spent than the budget for the completed work (cost variance CV = EV − AC = −¥1.5 million). In EVM, comparing the earned value (EV) with both the planned value (PV) and the actual cost (AC) evaluates progress and cost on the same monetary scale.

  • A. Correct. SPI = 6 ÷ 8 = 0.75 and CPI = 6 ÷ 7.5 = 0.8, both less than 1.
  • B. This computes CPI the wrong way round, as AC ÷ EV. CPI = EV ÷ AC = 0.8, so the project is over budget.
  • C. This computes SPI the wrong way round, as PV ÷ EV. SPI = EV ÷ PV = 0.75, so the project is behind schedule.
Practice this topic Back to topic

Related calculators

Books on Software Development and Project Management Ad

As an Amazon Associate I earn from qualifying purchases.

More Software Development and Project Management questions

  1. In a project with a budget at completion (BAC) of ¥12 million, the current planned value (PV) is ¥6 million, the earned value (EV) ¥4.8 million and the actual cost (AC) ¥6 million. Assuming the current cost efficiency continues, what is the estimate at completion (EAC)?
  2. In a software project that is behind schedule, the number of developers was increased from 5 to 10. By what factor does the number of communication paths between two people (the number of pairs) increase?
  3. Which project risk response shifts the impact to a third party, for example by taking out insurance against the losses if the risk occurs, or by having a specialist company take on the work under a contract?
  4. Which describes the function point method used to estimate software size?
  5. The SLA for a service specifies a monthly availability of at least 99.95%. A month is taken as 30 days, and planned downtime is included in the calculation. This month the service has already been down for a total of 15 minutes due to failures. How much more downtime is allowed for the rest of this month while still meeting the SLA?