Software Development and Project Management

A three-point estimate of an activity's duration gives an optimistic value of 4 days, a most likely value of 7 days and a pessimistic value of 16 days. What is the expected duration given by the PERT formula?

  1. A7 days
  2. B8 days
  3. C9 days
Show answer and explanation

Answer: B. 8 days

The PERT three-point estimate gives the expected value as (optimistic + 4 × most likely + pessimistic) ÷ 6, so (4 + 4 × 7 + 16) ÷ 6 = 48 ÷ 6 = 8 days. It is longer than the most likely value of 7 days because the pessimistic value lies far away. The standard deviation, an indicator of the spread, is (pessimistic − optimistic) ÷ 6 = 2 days. 9 days is the simple average of the three values, (4 + 7 + 16) ÷ 3.

  • A. This is the most likely value itself; it does not include the effect of the pessimistic value lying far away.
  • B. Correct. (4 + 4 × 7 + 16) ÷ 6 = 8 days.
  • C. This is the simple average of the three values; PERT gives the most likely value four times the weight.
Practice this topic Back to topic

Related calculators

Books on Software Development and Project Management Ad

As an Amazon Associate I earn from qualifying purchases.

More Software Development and Project Management questions

  1. In a project with a budget at completion (BAC) of ¥20 million, at a certain point the planned value (PV) was ¥8 million, the earned value (EV) ¥6 million and the actual cost (AC) ¥7.5 million. Which correctly describes the project's status at that point?
  2. In a project with a budget at completion (BAC) of ¥12 million, the current planned value (PV) is ¥6 million, the earned value (EV) ¥4.8 million and the actual cost (AC) ¥6 million. Assuming the current cost efficiency continues, what is the estimate at completion (EAC)?
  3. In a software project that is behind schedule, the number of developers was increased from 5 to 10. By what factor does the number of communication paths between two people (the number of pairs) increase?
  4. Which project risk response shifts the impact to a third party, for example by taking out insurance against the losses if the risk occurs, or by having a specialist company take on the work under a contract?
  5. Which describes the function point method used to estimate software size?