Software Development and Project Management

A project has the following activities, durations and predecessors: A: 6 days (none); B: 4 days (none); C: 4 days (A); D: 4 days (A and B); E: 2 days (C); F: 3 days (D), and its total duration is 13 days. The extra cost of shortening each activity by one day is ¥300,000 for A, ¥50,000 for B, ¥100,000 for C, ¥200,000 for D, ¥80,000 for E and ¥250,000 for F. Which is the cheapest way to shorten the total project duration by one day?

  1. AShorten activity B by 1 day (¥50,000)
  2. BShorten activity D by 1 day (¥200,000)
  3. CShorten activity A by 1 day (¥300,000)
Show answer and explanation

Answer: B. Shorten activity D by 1 day (¥200,000)

The critical path is A → D → F (6 + 4 + 3 = 13 days); the other paths are A → C → E at 12 days and B → D → F at 11 days. To shorten the project, an activity on the critical path must be shortened, and the cheapest of them is D at ¥200,000, after which A → D → F and A → C → E both take 12 days. B is the cheapest of all, but it is not on the critical path, so shortening it leaves the project at 13 days. Shortening A also gives 12 days, but it costs ¥300,000. Shortening activities by spending money in this way is called crashing.

  • A. B is not on the critical path, so shortening it leaves the project at 13 days.
  • B. Correct. It is the cheapest activity on the critical path, and the project becomes 12 days.
  • C. The project becomes 12 days, but it costs ¥100,000 more than D.
Practice this topic Back to topic

Related calculators

Books on Software Development and Project Management Ad

As an Amazon Associate I earn from qualifying purchases.

More Software Development and Project Management questions

  1. A three-point estimate of an activity's duration gives an optimistic value of 4 days, a most likely value of 7 days and a pessimistic value of 16 days. What is the expected duration given by the PERT formula?
  2. In a project with a budget at completion (BAC) of ¥20 million, at a certain point the planned value (PV) was ¥8 million, the earned value (EV) ¥6 million and the actual cost (AC) ¥7.5 million. Which correctly describes the project's status at that point?
  3. In a project with a budget at completion (BAC) of ¥12 million, the current planned value (PV) is ¥6 million, the earned value (EV) ¥4.8 million and the actual cost (AC) ¥6 million. Assuming the current cost efficiency continues, what is the estimate at completion (EAC)?
  4. In a software project that is behind schedule, the number of developers was increased from 5 to 10. By what factor does the number of communication paths between two people (the number of pairs) increase?
  5. Which project risk response shifts the impact to a third party, for example by taking out insurance against the losses if the risk occurs, or by having a specialist company take on the work under a contract?