Software Development and Project Management
In a WBS, which breaks down a project's deliverables and work hierarchically, what is the element at the lowest level, used as the unit for estimating duration and cost and assigning people?
- AWork package
- BMilestone
- CGantt chart
Show answer and explanation
Answer: A. Work package
A WBS (work breakdown structure) breaks down the deliverables of a project and the work needed for them into a tree, from the top level to lower levels. The elements at the lowest level are called work packages, and they are the units for estimating, scheduling, assigning people and tracking progress. A milestone is a significant point in time, such as 'basic design completed', used to check progress. A Gantt chart shows the schedule with tasks drawn as horizontal bars, and is used to draw the schedule of the work broken down in the WBS.
- A. Correct. It is the lowest element of the WBS and the unit of estimation and control.
- B. This is a significant point in time (a zero-duration checkpoint) for checking progress, not a unit of work.
- C. This is a chart that shows the schedule of tasks as horizontal bars, not an element of the WBS.