Yield and quality control
What is the correct order of the PDCA cycle used in quality control and process improvement?
- APlan → Do → Check → Act
- BDo → Plan → Act → Check
- CCheck → Act → Plan → Do
Show answer and explanation
Answer: A. Plan → Do → Check → Act
The PDCA cycle continuously improves quality and operations by repeating four stages: make a plan (Plan), carry it out (Do), evaluate the results (Check) and take corrective action (Act).
- A. Correct. Plan, Do, Check, Act.
- B. Doing before planning reverses the order.
- C. Starting from Check is not the PDCA order.