Software Development and Project Management

Which method of reviewing design documents or source code is led by a moderator, assigns roles to the participants, is carried out formally using checklists and the like, and records the defects found and confirms their correction?

  1. AInspection
  2. BWalkthrough
  3. CRound-robin review
Show answer and explanation

Answer: A. Inspection

An inspection is the most formal type of review, in which a moderator manages everything from planning and running the meeting to confirming the fixes (follow-up). Participants prepare in advance and look for defects using checklists, and the number and types of defects found are recorded, which can be used to evaluate and improve quality. A walkthrough is led by the author, who explains the work product step by step while the participants look for errors. A round-robin review is a method in which participants take turns acting as the leader or reviewer.

  • A. Correct. It is a formal review led by a moderator that uses checklists and records of defects.
  • B. This review is led by the author explaining the content, and it is less formal than an inspection.
  • C. In this method participants take turns acting as the leader or reviewer.
Practice this topic Back to topic

Related calculators

Books on Software Development and Project Management Ad

As an Amazon Associate I earn from qualifying purchases.

More Software Development and Project Management questions

  1. After a firmware version known to work correctly there are 1,000 commits, and the latest commit has a bug. The bug was introduced by one commit and occurs in every commit after it. When the culprit commit is identified by binary search, as with git bisect, what is the maximum number of times the firmware must be built and tested?
  2. In a WBS, which breaks down a project's deliverables and work hierarchically, what is the element at the lowest level, used as the unit for estimating duration and cost and assigning people?
  3. In an arrow diagram with nodes ① to ⑥, the activities, written as 'name: start node → end node, duration', are A: ① → ②, 6 days; B: ① → ③, 4 days; C: ② → ④, 4 days; D: ③ → ⑤, 4 days; E: ④ → ⑥, 2 days; F: ⑤ → ⑥, 3 days; and a dummy activity: ② → ③ (duration 0). What is the shortest duration of the whole project?
  4. A project has the following activities, durations and predecessors: A: 4 days (no predecessor); B: 2 days (none); C: 3 days (A); D: 2 days (B); E: 5 days (C); F: 4 days (C and D); G: 2 days (F). If all other activities start as early as possible, what is the maximum number of days by which the start of activity B can be delayed without extending the total project duration?
  5. A project has the following activities, durations and predecessors: A: 6 days (none); B: 4 days (none); C: 4 days (A); D: 4 days (A and B); E: 2 days (C); F: 3 days (D), and its total duration is 13 days. The extra cost of shortening each activity by one day is ¥300,000 for A, ¥50,000 for B, ¥100,000 for C, ¥200,000 for D, ¥80,000 for E and ¥250,000 for F. Which is the cheapest way to shorten the total project duration by one day?